Project Description

Fíor were brought onto this project when a push for completion was required when numerous packages still required procurement. We procured all the remaining packages within a tight deadline working with Wates Project Manager who we had worked with previously and agreed the final account on behalf of our clients at Wates Construction less than 4 weeks from Practical Completion being awarded.